General features of Middle Tamor Hydropower project are presented below
General
Installed capacity |
57 MW (as per license granted by DoED)
|
|
Project Location :
|
Taplejung district
|
|
|
Linkhim/Khejenim/Hadewa/Sawadin and Phurambu VDCs,
|
|
Zone :
|
Mechi Zone
|
|
Development region :
|
Eastern Development Region
|
|
Nearest highway :
|
Mechi Highway
|
|
Nearest Roadhead
|
Phunglin Bazaar, Taplejung
|
|
Climate :
|
Sub-tropical, Temperate & Alpine
|
|
Average temperature:
|
Maximum : 18° in April
|
|
|
Minimum : -0.3° in February
|
PROJECT LOCATIONS
Boundary Points |
Locations
|
|
Longitude
|
Latitude
|
|
1
|
87° 42’ 40” E
|
27° 27’ 09” N
|
|
2
|
87° 42’ 40” E
|
27° 23’ 57” N
|
|
3
|
87° 40’ 18” E
|
27° 23’ 57” N
|
|
4
|
87° 40’ 18” E
|
27° 27’ 09” N
|
HYDROLOGY
|
|
| Catchment Area |
1962 km2 |
|
Annual mean flow
|
107.7 m3/s
|
|
Maximum discharge
|
3770 m3/s (11 August 1987, 6760 m3/s at Gauging station 690, Mulghat)
|
|
Minimum discharge
|
8.09 m3/s (17 March 1965, 26 m3/s at Gauging station 690, Mulghat)
|
|
Design discharge
|
100 m3/s(33.3 % excedence of flow)(Tailwater tapping from Upper Tamor HP)
|
Project Components
Inverted Siphon 5m wide,4 m high ,80 m long , 2 chambered
Headrace Canal Trapezoidal reinforced concrete canal ,85 m long
Headpond Surface, volume : 13650 m3 , 2 min storage time
Head race Tunnel 3.1 km(approx)
Surge Tank 20 m dia. ,70 m long
Power House Semisurface
Turbine 5 units,Francis Turbine |